This page begins after receiving has identified what was actually accepted and the allocation record has shown what remains unavailable. Its job is to keep the supplier obligation visible without inventing a delivery promise.
Worked scenario: a cattle-fence order has three open lines: two woven-wire rolls, forty line posts and one gate assembly. The quantities are illustrative only. Keep every row in the purchase order's original unit and product identity.
01 · Open the action
Freeze the facts before asking for a date.
Start with the PO line, item or manufacturer identity, original ordered unit, quantity ordered, quantity accepted, receiving discrepancy reference and the remaining gap. California's procurement manual describes documenting partial shipments and discrepancies while keeping the order open until obligations are complete. New York's receiving guidance separates receipt inspection from later technical or functional inspection.
That boundary matters: a supplier follow-up record can say that two rolls remain open; it cannot quietly convert a held or unidentified roll into accepted stock.
Editable shortage ledger
Test how much of the open gap has a recorded commitment.
Edit the example. “Committed” means a quantity tied to a supplier response and promised date; it does not mean delivered, accepted or available to install.
| Item / unit | Ordered | Accepted | Committed | Follow-up state | Uncovered gap |
|---|---|---|---|---|---|
| Woven wire rolls |
|||||
| Line posts pieces |
|||||
| Gate assembly sets |
*The first two totals mix unlike units and are only row-control signals. Never buy or report a combined quantity across rolls, pieces and sets.

02 · Record the promise
A useful response has an object, quantity and date.
-
Name the exact obligation
Use the PO line and product identity. Do not ask only when “the fence order” will arrive if several lines have different status.
-
Attach the discrepancy evidence
Reference the packing slip, count, damage or identity hold and receiving date. RIT's procurement manual tells receivers to report shortages or discrepancies promptly with the PO number and supplier.
-
Capture the supplier action
Record whether the supplier will ship the balance, correct documents, investigate, cancel a line or propose a substitute. A proposed substitute stays outside the accepted quantity until its own review is complete.
-
Give the action an owner
Name the buyer or coordinator who will follow up, the promised date, the next check date and the fence section or schedule point affected.
-
Close with evidence
Link the later receiving record, approved change, cancellation or other authorized disposition. Do not close a line merely because an email thread became quiet.
03 · Escalation boundaries
Separate a late promise from a changed requirement.
If the supplier cannot meet the required point, the project may need a schedule decision, reallocation, approved substitution or commercial remedy. This page does not choose among them. Route each question to the delegated owner and keep the original requirement visible until an authorized decision changes it.
- Receiving issue: actual count, condition, document mismatch or unidentified material.
- Supplier action: acknowledged balance, correction, investigation and promised date.
- Technical review: product equivalence, interfaces, installation or safety implications.
- Commercial decision: pricing, cancellation, damages, payment hold or contract interpretation.
04 · Buyer questions
Questions that keep shortage records honest.
What fields belong in the record?
PO line and item identity, original unit, ordered and accepted quantities, open gap, evidence reference, supplier response, promised quantity and date, owner, affected section and closure evidence.
Should a partial delivery be marked complete?
No while the applicable obligation remains open. Record the actual receipt and keep the balance visible under the organization's procurement process.
Can a verbal promise close the shortage?
Log the discussion, then obtain the durable acknowledgement required by your process. Closure needs evidence of the resolved obligation, not only a conversation.
Can a substitute count against the gap?
Not automatically. Identify it and route it through approved technical and commercial review first.
What if the units differ?
Stop the comparison until the relationship between packages, rolls, pieces, feet or sets is approved and documented.
When is the item closed?
When the exact obligation is resolved and linked to accepted receiving, an approved change, cancellation or other authorized closure evidence.
Evidence register
Sources and limits.
These public procurement sources support traceable receipt and follow-up practices. They do not interpret a private contract, approve the example quantities or replace project-specific procedures.
Video decision: DO_NOT_ADD (4/12). A generic receiving or supplier-call video cannot verify this order's item identity, accepted quantity, authorized response or promised date. The editable record and cited procedures better serve the decision.