Worked procurement case · 3 work sections · 5 item groups

Allocate the delivery. Keep the shortage visible.

A partial shipment can support a bounded work section without pretending the whole order is complete. This example separates accepted stock, held stock, section reservations and the remaining purchase gap.

Planning example—not receiving acceptance or construction release. Use the purchase order, approved inspection process, current drawings and authorized project decision. Do not allocate damaged, unidentified, held or unapproved substitute materials.
Five stock groups.
Three fence sections.
One visible gap.

The example assumes the receiving record has already separated accepted items from discrepancies. It does not change any contract status. The purpose is narrower: reserve accepted quantities to a named section, prevent double-allocation and convert the unfilled quantity into a purchasing action.

Scenario: North boundary is the first priority, cattle lane is second, south subdivision is third. Quantities below are illustrative, not design recommendations. Replace them with the approved bill of materials and original units.

01 / Scenario inventory

Read each item as its own stock position.

One material can be complete while another blocks the same work section. Preserve the item identity and unit; do not pool unlike posts, rolls, fasteners or hardware.

FW-01 · woven wire

Rolls

Planned 8; accepted 6; none held. Reserve 4 north, 2 lane, 0 south.

Ready
6 rolls
Gap
2 rolls
LP-02 · line posts

Steel posts

Planned 180; accepted 150; 10 held for identity review.

Allocatable
140 pcs
Gap
40 pcs
BP-03 · brace posts

Wood posts

Planned 24; accepted 24; all available to the mapped terminal assemblies.

Ready
24 pcs
Gap
0 pcs
GT-04 · gates

Gate assemblies

Planned 3; accepted 2. Keep opening, hinge and latch interfaces tied to gate ID.

Ready
2 sets
Gap
1 set
HW-05 · hardware kits

Brace / gate kits

Planned 7; accepted 7; 1 held because its package identity is incomplete.

Allocatable
6 kits
Gap
1 kit
Control boundary

What “ready” means here

Available for allocation review only. It does not prove conformity, site readiness or authorization to install.

Substitutes
Hold
Unknown unit
Hold
02 / Editable ledger

Replace the example quantities with your approved material plan.

Enter the required quantity, accepted ready quantity and any part of that accepted stock that is still held. The calculator shows the purchase gap only; it does not approve allocation or release work.

Item / original unitRequiredAcceptedHeldPurchase gap
Woven wirerolls
2
Line postspieces
40
Brace postspieces
0
Gate assembliessets
1
Total required*215
Total allocatable*182
Total gap*43

*Totals combine unlike units only as a row-count check; never use the combined number as a purchasing quantity. Buy and allocate each item in its own unit and product identity.

Representative allocation review using a pasture section map, hardware samples and quantity tokens
Reserve by section, not by optimism. Write the item ID, original unit, accepted quantity, held quantity, exact work section and reservation date. A colored zone or staging location is not evidence of product approval. This representative image is not a customer jobsite.
03 / Allocation sequence

Move from receipt evidence to a controlled purchase action.

A / Freeze

Use the current basis

Record PO and drawing revision, item code, unit and section requirement. If the basis differs, stop the calculation and reconcile the change.

B / Exclude

Remove held stock

Segregate damaged, unidentified, disputed or substitute material. Do not count it as available while review is open.

C / Reserve

Name the section

Assign accepted quantities to one section and date the reservation so the same stock cannot be promised twice.

D / Gap

Calculate item by item

Required minus allocatable equals the purchase gap, never less than zero. Keep each material in its original unit.

E / Route

Open a purchase action

Name the buyer, supplier query, required date and affected section. Route alternates through substitution review.

F / Release

Keep authority separate

Only the authorized project process decides technical acceptance, site readiness and construction release.

04 / Questions from buyers

What a partial delivery does—and does not—allow.

Can one fence section start?

Possibly, but not because material simply arrived. Review the defined section against accepted quantities, current documents, site readiness, dependencies and authorized release.

What if the packing list and visible count differ?

Preserve both values in the receiving record. Allocate only the quantity accepted under the approved process, and route the discrepancy.

Can excess from one section fill another?

Only after confirming the same product identity, unit, revision, interfaces and authority. Record the transfer so reservations remain traceable.

Can an alternate product close the gap?

Not automatically. Keep it on hold and use the material substitution review before changing the allocated requirement.

Should every item have a buffer?

There is no universal percentage. Use the approved plan, packaging, expected waste basis, site risk, lead time and documented project decision.

How is the shortage closed?

Record the purchase or approved change reference, quantity, due point, receiving evidence and the person who clears the open allocation.

Evidence and limits

NRCS Fence Standard 382 supports a mapped fence layout, gate locations, material quantities and requirements, plus ongoing inspection. Penn State Extension describes selecting fence types around purpose, topography, access, gates and existing infrastructure. These sources support a controlled material plan; they do not approve this example's quantities or release a project.

Video decision: DO_NOT_ADD (4/12). A generic unloading or fence-building video cannot establish the accepted stock, order revision or release authority for a particular shipment.