What date are we comparing?
Keep at least three dates separate: the required project need point, the supplier's supported delivery date, and the next internal decision date. FAR Subpart 11.4 treats delivery or performance time as an essential schedule element and notes that construction scheduling considers material availability and multiple completion dates.
A supplier ETA is evidence only when its source and checked date are preserved. It does not automatically revise the required date. If the project basis changes, record that through the authorized change process.